Owner: Metropolitan Washington Airport Authority
General Contractor: The Lane Construction Company
Location: Loudoun County, Virginia
Contract Value: $1.2 Million
Completion Date: August 2004
Description:
The east-west runway 12/30, after more than 40 years in service, was completely reconstructed in a record four months. This fast tracked program minimized the impact on flight operations and was completed in time for a new airline's ramp-up of service.
Midasco installed nearly 400 runway lights and associated power systems with 30 people working around the clock in order to meet the tight construction schedule.