Woodrow Wilson Corridor Interchange Projects
 
 

Owner:  Maryland State Highway and Virginia Department of Transportation

General Contractors:  G.A. and F.C. Wagman and Corman Construction

Location:  Prince George County, Maryland and Alexandria, Virginia

Multiple Contract Value:  $19.9 Million

Completion Date:  Expected December 2008

The Woodrow Wilson Bridge Project is replacing almost 12 percent of Interstate 95 (the Capital Beltway) with two new wider bridges, four new interchanges and Beltway improvements throughout its 7.5...

hardhat
Woodrow Wilson Bridge Project
 
 

Owner:  Maryland State Highway Administration

General Contractor:  Virginia Approach Constructors, A Joint Venture of Corman Construction and Granite Construction

Location:  I-495 crossing Potomac River between Maryland and Virginia

Contract Value:  $7.4 Million

Completion Date:  May 2008

The Potomac River Bridge project involves the construction of twin 6-lane replacement bridges for the existing Woodrow Wilson Bridge. The new bridges include double leaf bascule spans over the main...

hardhat
Springfield Interchange Projects
 
 

Owner:  Virginia Department of Transportation

General Contractors:  Shirley Contracting Company, The Lane Construction Company, Archer-Western Contractors

Location:  Springfield, Virginia

Multiple Contract Value:  $22.7 Million

Completion Date:  June 2007

Springfield Interchange was an eight year; $676 million project undertaken by VDOT to improve one of the most heavily travelled interchanges in the nation. The interchange included 24 lanes at its widest...